Client
Costain
Main Contractor
Midas Construction
Approx Value
Sector
Commercial

Description of Works:

Keyplan Engineering were appointed to carry out the design, supply, installation, testing & commissioning of the mechanical services modifications to the 2nd floor office reconfigurations and the conversion of existing warehouse unit into development lab and goods inwards space, general description as follows:

2nd Floor LiveWest – Modification of existing office floor plate to accommodate new cellularised meeting rooms, kitchenette and open plan office space.

WestOne Building – Complete fit out of the existing commercial unit shell to form a new development lab & goods in space.

Systems & Services:

  • ASHP (Air Source Heat Pump)
  • Radiant Heating
  • Warm Air Heating
  • BMS (Building Management System)
  • Chilled Water
  • Low Temperature Hot Water Heating
  • Fan Coil Units
  • Server Room Cooling (Split AC Systems)
  • Drainage
  • Mains Cold Water
  • Hot Water (via ASHP)
  • Trace Heating
  • Thermal Insulation
  • Water Treatment
  • Commissioning

Systems & Services:

  • ASHP (Air Source Heat Pump)
  • Radiant Heating
  • Warm Air Heating
  • BMS (Building Management System)
  • Chilled Water
  • Low Temperature Hot Water Heating
  • Fan Coil Units
  • Server Room Cooling (Split AC Systems)
  • Drainage
  • Mains Cold Water
  • Hot Water (via ASHP)
  • Trace Heating
  • Thermal Insulation
  • Water Treatment
  • Commissioning

"Midas has now achieved successful Practical Completion and Handover of the above project & I wanted to send a note of thanks to you and your team for all their efforts in what was a challenging project. This followed on from the successful Costain project completed last year at the same building development. Experience gained during the Costain project prepared us well to foresee and solve challenges that LiveWest brought.

Keyplan and Midas experience and knowledge of the building is one of the reasons why the client selected us to complete this refurbishment for them and feedback so far indicates they are extremely satisfied with the end product. One particular achievement was to finally resolve their historical issues with the faulty BMS and ventilation systems, which could not have been done without your involvement."

Micky Kent, Building Services Manager
Midas Construction